May 2026 Update

The Final Stage is well and truly out of the ground. Across all four buildings, structural work is progressing steadily. Here's where things are at this month.

Building A - Level 2: Precast panel installation is complete, and the final post-tension stressing of the Level 2 slab has been finished. This is a key structural milestone, the building is gaining its full form above ground.

Building B - Upper ground / Level 1: Formwork construction for the Level 1 slab is underway, with services set-out and installation progressing within the slab. The groundwork that makes these apartments function, power, plumbing, infrastructure, is being locked in at every level as construction moves upward.

Building C - Upper ground: Services set-out to the upper ground slab is in progress, alongside beam reinforcement work. The structural skeleton of Building C is taking shape.

Building D - Level 1: Precast panel installation is underway and formwork construction for Level 1 is progressing. Building D is following closely behind the other buildings as the build moves through each level.

Basement - Building A: Formwork stripping of the basement in Building A is complete, clearing the way for the next phase of works.

The 78 corner apartments that make up The Henry Final Stage are being built above a full Health Hub, on a site that is active, progressing, and on track for a December 2027 occupancy.